Reading Time: 3 minutes

Plants and equipment are often used in construction works to save time, labour and cost. Plants used in the construction industry are many and they include: pile driving equipment, tower crane, concrete mixers, pumps, excavators, scaffolds, demolition plants, hoists, compressors, bulldozers, power tools etc. The use of plants and equipment in construction works always come with large costs and these are factored at the billing stage of the project. Large companies may have necessary equipment available to them but smaller companies when given a project may be in the need to hire or buy necessary equipment. The decision to buy or hire an equipment is guided by some factors listed below:

Factors to determine whether to buy or hire an equipment

1. What will the machine do?

2. Will skilled operator have to be employed?

3. Working life of the machine.

4. Power source.

Plants/equipment are mechanical instrument. To ensure that they stay longer in service, endeavour to

1. Keep the plants clean always.

2. Keep them in good working condition.

3. Regularly maintain them.

4. Use machine for the work they were made to do.

5. Keep statutory records of the equipment.

Plant/equipment cost rates

The cost to the builder of the use of plant/equipment comes about as follows:

1. Initial cost

2. Scrap value

3. Estimated life period

4. Depreciation

5. Licence and insurance

6. Repairs and maintenance

7. General overhead (cost of admin)

8. Profits

How to determine total cost of plant per hour: Total cost of plant per hour includes cost of the plant, cost of operation of the plant, overhead and profit.

How to determine cost per hour of a plant/equipment

To determine the cost per hour of a plant, it is necessary first to determine the total working hours per year by the following process

Total number of weeks in a year = 52 weeks                   

Assuming holiday period = 3 weeks                        

Maintenance period of plant = 2 weeks                          

Time to transport plant to site = 1 week                       

Idle time/breakdown = 8 weeks                                

Total working hours in a week = Total number of weeks – (holiday period + maintenance period + transport period + idle time) = 52 – (3 + 2 + 1 + 8) = 52 – 14 = 38 weeks.

Working days per week     = 5

Working hours per day  = 8                                

Working hours per week = 8 x 5  = 40 hours                

Assuming half-day work on Saturdays   = 4 hours       

Total working hours per week = 40 + 4    = 44 hours    

Total working hours per year = total working hours per week x total working week per year = 44 x 38 = 1672 hours

If the cost of plant per year = N 1,000,000

Cost of plant per hour = cost of plant per year/number of hours per year = 1,000,000/1672 = N 586.09 per hour

How to determine operation cost per hour of a plant/equipment

To use an equipment in a day, the following costs are involved:

Machine operator: 8 hours @ N 1,000 per hour = N 8,000

Diesel per day    = N 9000                                                        

Oil per day  = N 2,000                                                         

Grease or rags = N 500                                                           

Total cost per 8-hour day  = N 19,500                                    

Cost per hour = cost per day/number of hours in a day = 19,500/8 = N 2,437.5

Total cost per hour = cost of plant per hour + cost of operation of plant per hour = 586.09 + 2437.5 = N 3,023.59

Add 10% overhead = N 302.359

Total = N 3,325.949

Add 10% profit = N 332.595

Total = N 3,658.544

How to determine production capacity of a plant (using concrete mixer for example)

154 m3 of concrete is required to be produced and placed in foundation in 6 days, check whether a 0.35 m3 capacity mixer would be suitable to do the job.

Actual production time of the equipment assuming 80% actively working in a day = 0.8 x 8 (hours per day) x 6 (days) = 38.4 hours

Required output of the mixer per hour = volume of concrete/ total number of hours = 154/ 38.4 ≈ 4 m3 of concrete per hour.

Mixing cycle of concrete is as follows:

Loading time to mixer                        = 1 minute

Mixing time in mixer                          = 3 minutes

Discharge time from mixer                 = 1 minute

Total = 5 minutes                                = 0.0833333 hours

This implies that using the mixer, one batch of 0.35 m3 concrete is completed in 0.0833333 hours

In one hour, 0.35/0.08333333 = 4.2 m3 of concrete would be produced.

This value (4.2 m3) is greater than the calculated required output (4 m3) per hour for the mixer. This implies that the mixer can produce 4.2 x 38.4 = 161.28 m3 of concrete in 6 days which is higher than the required value of 154 m3. Therefore, the mixer is adequate for the work. Where the mixer capacity is less, it may be required to go for a larger mixer or increase the number of days of the work.

Thanks for reading!

Share.

An inquisitive engineer with considerable skills in analysis, design and research in the field of civil engineering.

Leave a ReplyCancel reply

Exit mobile version